1) No.2  Steel Making Plant of Baotou Steel (Sheet Plant)

Major Equipment: 2 sets of 230t Converter, 2 sets of LF, 2 sets of RH, 1 set of 2-strand CSP and 1 set of single strand wide thick slab caster.

Mode of Service: Engineering Design + Technical General Contracting

Production Capacity: about 4,200,000t/a

Year of put-into-operation: 2000/2007

Characteristics: One of the firsts to combine large scale converter with dry type dedusting device;

Application of sub lance system, enabling dynamic control over steel making process;

Set an international precedent for large scale converter to match up with double strand thin slab caster.

Awards and Prizes: The project was constructed in 2 phases. The phase I project won the “China Building Construction Luban Awards for the year of 2002” and “National Engineering Design Bronze Prize for the year of 2004” while phase II project won “Metallurgy Excellent Design First Prize for the year of 2009”

 

2) Hebei Qian’an Yanshan Iron and Steel Co., Ltd.

Major Equipment: 1 set of 180t de-P converter, 3 sets of 180t steel making converter, 3 sets of LF, 1 set of VD, 1 set of RH, 1 set of 10-strand billet caster, 1 set of 8-strand bloom caster and 2 sets of slab caster.

Mode of Service: Engineering Design + Equipment Package Supply

Year of put-into-operation: 2010

Production Capacity: about 6,000,000t/a

Characteristics: duplex converter smelting arrangement;

Application of sub lance system, enabling dynamic control over steel making process;

         Teamwork of diversified refining facilities and multi-sized casters

 

3) No.1  Steel Making Plant of Baotou Steel

Major Equipment: 2 sets of 150t converter, 2 sets of LF, 1 set of VD, 1 set of 8-strand billet caster, 1 set of 6-strand bloom caster, mainly producing steels for construction such as carbon constructional steel, welding wire steel, etc. and high speed heavy rail steel.

Mode of Service: Engineering Design + Technical General Contracting + Equipment Package Supply

Year of put-into-operation: 2010

Production capacity: about 3,000,000t/a

Characteristics: Application of sub lance system, enabling dynamic control over steel making process;

             The first heavy rail producing line domestically designed

 

4) Laiwu Steel Group

Major Equipment: 3 sets of 120t converter, 2 sets of LF, 1 set of 3-strand beam blank caster and 2 sets of slab caster, mainly producing carbon constructional steel, welding wire steel and construction steels and hot rolled plates.

Mode of Service: Engineering Design

Year of put-into-operation: 2003

Production capacity: about 4,200,000t/a

Characteristics: duplex converter smelting arrangement;

Application of sub lance system, enabling dynamic control over steel making process;

         The biggest beam blank production line in China at that time.

 

5) Xuanhua Iron and Steel Co., Ltd.

Major Equipment: 2 sets of 80t converter, 2 sets of LF, 2 sets of billet caster.

Mode of Service: Engineering Design

Year of put-into-operation: 2001

Production capacity: about 2,100,000t/a

Characteristics: 3-point bottom-suspended spherical hinge

 